Evans Pump Station-#1 Pump and Motor RebuildFollowing the decision to rebuild the Evans pump #2 in 2021 for mechanical wear issues, but unexpectedly discovering severe cavitation damage to the…
Evans Pump Station-#2 Pump and Motor Rebuild (pic heavy)In 2019 the Evans Pump #2 experienced a small electrical fire within the motor. Vibration testing conducted in 2020 showed alert levels in the motor…
Smith Pumping Plant Foundation ReplacementIn December of 2020, the Smith Pumping Plants' original wood and concrete sump foundation failed. Large sinkholes developed where the foundation…
CRPUD Awards Grant to Scappoose Drainage Improvement CompanyDeer Island, OR - May 26, 2020 - Columbia River PUD awarded the Scappoose Drainage Improvement Company (SDIC) an Economic Development Grant for $7,500…